2025 Street Improvement Projects

Construction Updates

Look here for weekly updates to each project area during construction. All updates are subject to change due to weather or other circumstances.

Icon of computer mouse pointer clickingView interactive maps of our projects

Types of Street Improvements

Reconstruction

work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, water main replacement, and replacement of curbs.

Reclamation

work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Rehabilitation

work consists of replacing the top 2" of pavement and minor utility work.

Special Assessment Payments

The interest free pre-payment period began on May 7th and will be available through 11/15/2025. There are three payment options:

Assessments not paid by 11/15/2025 will be sent to Dakota County Taxation for certification to your 2026 property taxes.

Please call Molly at 952-895-4495 with any questions.

Project Timeline

  • June 18, 2024: Council ordered preliminary report for the 2025 Street Improvement Projects
  • June - November 2024: Staff studied project areas and drafted a preliminary report
  • October 3, 2024: Open House at Fire Station 1
  • October 8, 2024: Open House at North River Hills Park
  • November 20, 2024: Open House at City Hall
  • December 17, 2024: Council received preliminary report and called for public improvement hearing
  • February 4, 2025: Council held public improvement hearing
  • March 2025: Received bids
  • April 8, 2025: Council awarded construction contracts
  • May 6, 2025: Council held assessment hearing
  • May - October 2025: Construction
  • October 2025: Council to hold assessment hearing for the Southwest Burnsville project area
  • November 15, 2025: Assessment pre-payment deadline
  • Spring 2026: Final completion

Dates are tentative and subject to change.