Interior Renovations: Demolition and preparation work continued behind temporary walls in the existing city hall. Crews disconnected the old chillers and rerouted piping and electrical lines to maintain essential systems throughout co...
On the Grounds: Big changes are visible! Crews have begun installing structural steel and precast wall panels, marking the start of vertical construction. Foundation work is nearly complete, with the la...
Inside City Hall: Interior demolition has started! Crews are removing ceilings, walls, flooring, and mechanical systems in unoccupied areas to connect the existing building to the new C...
On the Grounds: Major site work continues. The construction team has nearly completed mass grading, and the first concrete footings were poured on July 15—an exciting milestone. Crews are now forming and pouring foundations for the new City Hall addition....
Breaking Ground: We broke ground with a celebration on May 22. Our Police and City leadership teams, elected officials and our project partners invited the community out to a fun event marking the occasion.
On the Grounds: Fences mark the construction site...
We are breaking ground on our Police City Hall facility renovation and we want you to celebrate with us!
May 225 - 7 p.m.5:30 p.m. Groundbreaking CeremonyCity Hall
Come view the construction equipment that makes this project possible and explore police, fire and other city vehicles. Grab dinner from a food truck, make your mark on a piece of the new building ...