2021 Street Maintenance Overlay

These Projects Include

  • 1.5" mill and overlay
  • Partial curb replacement
  • Water main replacement (Highland Area neighborhood only)
  • Repaving (Highland Area and Frontier Court only)

Contacts

Links

Updates

See phasing map below for reference

Week of September 20 - 25

See updates below by phase.  Click Construction Update (PDF) for a printable pdf version with more information.

Phase 1 - Highland Forest Area

  • No work planned for this week
  • During the week of September 27 - October 2
    • Install mailboxes
  •  Paving final layer of asphalt in Spring of 2022

Phase 2 - Highland Forest Area

  • Finish concrete sidewalk installation
  • During the week of September 27 - October 2
    • Install mailboxes
  • Paving final layer of asphalt in Spring of 2022

Phase 3 - Highland Forest Area

  • Site cleanup

Red Oak Area is complete!

Vista View Area is complete!

Heather Hills Drive is complete!

Frontier Court is complete!

Highland Forest Area Map