Northeast Area (2020)

Overview

Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.  These areas include:

  • River Hills Drive
  • Happe Area
  • North Highway 13 Frontage Road

Rehabilitation work consists of replacing the top 2" of pavement and spot replacement of curbs.  These areas include:

  • Parkwood Drive
  • Travelers Trail

Contacts

Links

Updates:

See phasing map below for reference

Updates for the week of June 1-6, 2020

See updates below by phase.  Click the Weekly Construction Update (PDF) for a printable pdf version with additional information.

Phase 1

  • Striping pavement (Includes dedicated on-street bike lanes on Travelers Trail)
  • Mulching and seeding disturbed boulevard areas

Phase 2 

  • Finishing pouring concrete curb and sidewalk spot replacement areas

Phase 3

  • Finish pouring concrete curb and sidewalk spot replacement areas
  • Start grading on River Hills Drive south of Red Oak Circle South

Phase 4

  • Reclaiming pavement mid week
  • Grading later in the week

Phase 5

  • Finishing installing storm sewer (16th Avenue just north of 122nd Street will be closed for this work)
  • Start removing concrete curb and sidewalk spot replacement areas late in the week
Northeast Area Phasing Map