Maple Island/Bluebill Bay Area

GovDelivery envelope logo Opens in new windowSubscribe to email updates

Overview

The Maple Island/Bluebill Bay Area is planned for 2019 street rehabilitation and reclamation. The street rehabilitation portion consists of spot curb repair, milling the top two inches of pavement, and placing a two-inch asphalt overlay. The street reclamation portion consists of grinding up of the existing asphalt while mixing it with the gravel base, grading, paving, storm sewer repairs and upgrades, and sanitary sewer repairs. Curbs will be spot replaced where severely cracked or broken.  This project is being managed by the City of Lakeville.  Additional information is available on their project website.

Contacts

Links

Updates

Click on your street segment on the map below or see below for updates.

August 16, 2019

Phase 8: Curb and gutter crews will get started on Tuesday 8/20.

August 8, 2019

Phase 8:  Curb and gutter removal and replacement activities are scheduled to start on Friday 8/16.

Phase 9: Utility crews are scheduled to start working on storm sewer improvements on Monday 8/12.  Curb and gutter removals and replacements started this week Tuesday 8/6.  Curb replacements are scheduled to finish Monday 8/12.  Reclaiming the existing asphalt street surface is scheduled to begin Wednesday 8/14 thru 8/15.