Lake Marion Trail

This Project Includes

  • Installation of new paved trails from Sunset Pond Park to Kelleher Park
  • Installation of a new boardwalk through part of Kelleher Park
  • Installation of off-street sidewalks from Kelleher Park to Savage
  • Installation of dedicated on-street bike lanes from Kelleher Park to Savage

Contacts

Links


Updates

See updates below by phase

Phase 1

  • Centerpoint Energy is finishing relocating a gas main
  • Retaining wall installation to start late in the week of August 17, 2020
  • Finishing grading the week of August 22, 2020

Phase 2

  • Grading is continuing till complete
  • Paving the trail is tentatively scheduled to start the first week in September 2020

Phase 3

  • Grading is continuing

Phase 4

  • Schedule yet to be determined

Phase 5

  • Grading is continuing until complete
  • Paving the trail is tentatively scheduled to start the first week in September 2020
  • Installing the concrete sidewalk is tentatively scheduled for the second week in September 2020
Lake Marion Trail Phasing Map