Southwest Area (2020)

This Project Includes

Rehabilitation work consisting of replacing the top 2" of pavement and spot replacement of curbs. The following are the areas included in this project:

~ Loop Road North~ Loop Road South
~ Marcia Ann Lane~ Brown Lane
~ Omeara Court~ 152nd St. West
~ Circle High Drive


Contacts

Links

Updates

See phasing map below for reference

August 17, 2020 Update

See updates below by phase.  Click the Construction Update (PDF) for a printable pdf version with additional information.

Loop Road, Marcia Ann Lane, Brown Lane, and Omeara Court

  • Finish restoring boulevards with topsoil/seed

Circle High Drive

  • Mowing and re-seeding has been completed
  • The City will be meeting with the Contractor the week of 8/17/2020 to review the boulevards and come up with a plan to get turf fully established
Southwest Area Phasing Map