Highland View Area

GovDelivery envelope logo Opens in new windowSubscribe to email updates

Overview

Reconstruction (northern half) consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs. Reclamation (southern half) consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map below or see below for updates.

June 12, 2019

The gas company is completing gas main replacement in the street reconstruction areas.  Temporary water main installation in Phase 2 is tentatively scheduled to start June 27, 2019.

May 29, 2019

Temporary water main installation in Phase 2 is tentatively scheduled to start June 17, 2019.  Contractor will drop off door notices prior to starting installation.

May 22, 2019

Interactive applications with information on street reconstruction and reclamation have been posted in the "Links" section of this page.  Please see the Street Reconstruction and Reclamation Informational Web App, the Street Reconstruction Process Overview, and the Street Reclamation Process Overview for more information.