Highland View Area

Overview

Reconstruction (northern half) consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs. Reclamation (southern half) consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Contacts

Links

Updates:

* You can also click on the map below for additional information

October 18, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): sodding is complete.  The contractor is finishing cleanup items and will be raising manhole and gate valve lids in the next week.
  • Phase 3 (Reclamation Areas): Final paving is scheduled the week of October 21, 2019.
  • Phase 4 (Highland View Avenue, Lane, and Circle):  The contractor is planning to ramp driveways with gravel Saturday, October 19, 2019 to allow residents back into their driveways.  Grading and preparation for street paving is scheduled for early in the week of October 21, 2019.  Paving the first layer of asphalt is scheduled in the middle of the week of October 21, 2019.  Installation of blacktop driveways and sod is scheduled the week of October 28, 2019. 

October 10, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): Sodding is nearly complete. Remaining sod will be placed the week of October 14, 2019, weather permitting.
  • Phase 3 (Reclamation Areas): Final paving has been delayed to the week of October 14, 2019 due to weather.
  • Phase 4 (Highland View Avenue, Lane, and Circle): Curb installation is tentatively scheduled for Friday, October 11, 2019 and Saturday, October 12, 2019. Grading is scheduled late in the week of October 14, 2019. Paving the first layer of asphalt is anticipated for the week of October 21, 2019.