Burnhaven Woods Area

GovDelivery envelope logo Opens in new windowSubscribe to Email Updates

Overview

Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map below or see below for the latest update. 

June 21, 2019

Storm sewer installation on James Avenue and 138th Street West is continuing until complete early in the week of June 24, 2019.  The pipe contractor will be working Saturday, June 22nd, 2019 until 5 pm doing pipe installation.  James Avenue from James Court to 138th Street West will remain closed through about June 26, 2019.

Pavement in Phase 2 is scheduled to be ground up starting June 24, 2019 and is expected to take 3-4 days to complete.  Grading will take place after grinding up the pavement.